Managing Organizational Risk Knowledge
Luciana de Landa Farias
(Federal University of Rio de Janeiro - COPPE, Brazil
delanda@cos.ufrj.br
Guilherme H. Travassos
(Federal University of Rio de Janeiro - COPPE, Brazil
ght@cos.ufrj.br
Ana Regina Rocha
(Federal University of Rio de Janeiro - COPPE, Brazil
darocha@cos.ufrj.br
Abstract: Risk planning
requires an organization global view, as it is strongly centered in the
experience and knowledge acquired in former projects. The larger the experience
of the project manager the better will be his ability in identifying risks,
estimating their occurrence likelihood and impact, and defining the mitigation
and contingency plans. However, project manager risk knowledge cannot stay
in an individual level, but it must be made available to the organization.
This paper describes an approach to risk planning in software projects
based on the organizational risk knowledge reuse. A risk management process
focused on the capture and utilization of organizational knowledge together
with a support case tool make part of this approach. An experimental study
of the relations between risk-causing facts and risks of software projects
was accomplished and its results used to define such a tool.
Keywords: Risks Management,
Knowledge Management, Risks Planning.
Categories: D.2.0, D.2.9
1 Introduction
It is becoming more difficult to
manage project risks due to the size and complexity of current software
products [Garvey et al., 1997]. Project managers
can inadvertently repeat past mistakes simply because they do not know
the mitigation actions which have been successfully applied or even because
they do not value risks caused by certain project restrictions and characteristics.
Inefficient risk knowledge management contributes to maximize this problem.
One of the reasons is the fact that project information concerning risk
management is in individuals' minds or distributed among various documents,
making its reuse difficult.
In a project, risks are those conditions or events whose occurrence
is not certain, but whether they occur may adversely affect the project.
Three aspects associated to a risk can be identified [Pfleeger
et al., 2001]: (i) the loss associated with the event; (ii) the likelihood
that the event will occur; and (iii) the degree to which event consequences
may be changed. Risks can be generic or project-specific. Generic risks
are those common to all software projects, such as requirements misunderstanding,
key personnel losing, or insufficient time for testing. Project specific
risks are threats that result from the particular vulnerabilities of the
given project and organization.
For example, a vendor might promise to deliver some necessary network
software at a particular date, but there is some risk that the software
will not be available on time.
The lack of documentation on the success or failure of past experiences
is one of the reasons for inefficient risk management utilization or non-utilization
in software development organizations. Besides risk management knowledge,
the past experiences analysis is fundamental to help project managers plan
and control risks. Statz [Statz, 1999] discusses
the importance of learning from the experience obtained in organization's
former projects, and proposes the lessons learned documentation in software
projects. Similarly, Markkula [Markkula, 1999] considers
the project experiences the most important source of knowledge in software
engineering, and describes the need of identifying and sharing the acquired
experience.
Risk planning can be enriched by using knowledge and experience acquired
by the various managers while working on the several organization projects.
In order to do that, it is necessary that risk knowledge be captured and
stored throughout projects development, so that it will make its future
utilization possible. However, without an infrastructure that can make
organization risk knowledge available it is very difficult to manage all
the acquired risk knowledge and experience.
Garvey et al. [Garvey et al., 1997] define
information architecture for risk management based on reusing experience
acquired in previous organization projects. Williams et al. [Williams
et al., 1997] show the results of experiences in using risk management
by describing lessons learned in the SEI risk program. The program works
with a database of software risks that supports the risk management activities.
Kontio and Basili [Kontio and Basili, 1996] describe
how data and experience acquired in measurements can be captured for risk
management purposes. They also describe the Riskit Method and its integration
with the Experience Factory framework.
The risk identification strategy proposed in this paper has some innovation
when compared with related works. The approach explores the relationship
between risks and particular software projects risk-causing facts, such
as those related to technology, planning, personnel and external factors.
A risk-causing fact is defined as any condition/restriction found or predicted
by the project manager at the software project initial stage (the planning
stage). Besides, a risk-causing fact is a potential cause of risks to the
project. Examples of risk-causing facts are "development team inexperienced
in software engineering", "project using innovative technology",
"lack of software development process". The proposed tool uses
knowledge acquired in similar projects and it is integrated into a software
development environment. It supports the activity of risk planning by making
available the organizational knowledge that might be useful to the project
manager during the activities of Identifying risks, Analyzing
risks, Prioritizing risks, Planning risk management and
Monitoring risks.
This paper is organized as follow: Next section presents our proposed
risk management process based on the ISO 10006 [ISO, 1997],
the technical report 16326 of the ISO/IEC [ISO/IEC, 1999],
and the IEEE standard for risk management [IEEE, 2001].
Such process emphasizes the use of organizational risk knowledge throughout
several activities. Section 3 describes the experimental
study of the relations between risk-causing facts and of software projects
risks, describing their objective and exemplifying the results. Section
4 discusses the approach we propose to risk planning, presenting the
Riskplan tool, which supports the several activities of the risk
management process. Finally, Section 5 makes some final
remarks and considerations.
2 Risk Management Process
Risk management is a continuous process that aims to systematically
treat risks throughout the software project lifecycle. Its objective is
to minimize the impact of potentially negative events, following and managing
the risks that might threaten the success of a project. The ISO 10006 standard
[ISO, 1997] recommends the use of experience and historical
data from former projects throughout all process activities. Therefore,
the process described in this document seeks the reuse of organizational
knowledge and experience, one of the benefits emphasized by Knowledge Management.
Figure 1 shows the risk management process that
is divided into the processes Evaluate Risks and Control Risks.
The process Evaluate Risks, on its turn, is divided into the activities
Identify risks, Analyze risks and Prioritize risks.
The process Control Risks is subdivided into the activities Plan
risk management, Integrate risk plan and Monitor risks.
Each of the activities is then divided into sub-activities, where the utilization
of organizational risk knowledge is recommended. The proposal is to support
the execution of this process, making it possible to capture and utilize
risk knowledge throughout the several activities performed.

Figure 1: Risk Management Process
The activity Identify risks is divided into the following sub activities:
- Identify risks originated from project decisions - During this
sub activity, the project manager has to analyze the decisions taken throughout
the project planning, trying to find risk-causing facts. All constraints,
suppositions e decisions must be reviewed in order to identify potential
problems caused by the decisions taken.
- Identify risks from similar projects - During this sub activity,
the project manager must analyze the problems occurred and the lessons
learned in previous similar projects, trying to find possible risks to
the on-going project.
- Identify other risks - Based on his/her previous experience
with risk management, project management and software engineering, the
project manager must analyze the risks identified up to the moment and
insert any other he/she might judge pertinent.
The product generated in the risk identification activity is the project
risk list. However, these risks still need to be analyzed and prioritized.
In the Analyze Risks activity, the project manager conducts the sub activities
ahead for each identified risk:
- Estimate risk occurrence probability - The qualitative estimate
must be always performed and the risk can be categorized as low probability
risk, medium probability risk or high probability risk. The quantitative
estimate is performed when possible. The analysis of the risks that occurred
in previous similar projects can help the execution of this sub activity.
If a particular risk occurred in various similar projects this might mean
that this is a risk with high probability of occurrence in the on-going
project.
- Identify risks causes and consequences - In this sub activity
it must be identified the risk occurrence causes and the consequences the
risk might bring to the development process and to the software product.
Again, the analysis of risk causes and consequences in previous similar
projects can help the execution of this sub activity.
- Estimate the risk occurrence impact - The impact can be categorized
as very high, high, medium or low. If necessary, a quantitative estimate
must also be conducted. If the risk occurred in similar projects, it must
be analyzed the caused impact in order to help the estimate.
The product generated in the risk analysis activity is the project risk
list updated with causes, consequences, occurrence probability and impact
of each identified risk. After that, the Prioritize Risks activity is conducted
and it is divided into the following sub activities:
- Compute the exposure to the risk value - For every identified
risk, the exposure to the risk is calculated. In case it is not possible
to perform quantitative estimates, the exposure to the risk must be computed
as follows: High probability and high impact risks receive a greater value
of exposure to the risk than the low probability and low impact risks.
The exposure to the risk in this case receives the value of the probability
given to the risk concerning the estimated probability and impact.
- List the risks in descendent order of exposure to the risk -
The purpose of this sub activity is to separate the most important risks
from the least important risks, making it possible the conduction of the
next sub activity.
- Define the set of risks that will be managed throughout the project
- Based on the exposure to the risk value associated to each risk, it is
defined a cut line. Only the most important risks are managed throughout
the project.
The product generated with the conduction of this activity is the project
risk list prioritized. It can then be started the conduction of the Control
Risks process, which first activity is the project risk management planning.
The Plan risk management activity is divided into the following sub activities:
- Define risk treatment strategy to each risk - It must be defined
the strategy that will be used to treat every project risk. It is helpful
to review the strategies adopted in the previous similar projects, verify
the strategies efficiency and then define how to treat the risk in the
on-going project. For every risk, the project manager must choose one of
the following strategies: avoid the risk, transfer the risk or assume the
risk.
- Establish the mitigation and contingency plans to the assumed risks
- A mitigation plan is developed to define a set of necessary actions to
minimize the risk consequences. The mitigation actions must reduce the
risk occurrence probability, the risk associated impact or both. It is
also important to develop a contingency plan that specifies the actions
to be taken in case some specific risk occurres. It is helpful to review
the risk planning performed in previous similar projects. If the risk occurred
in any similar project, it must be analyzed the efficiency of the defined
mitigation and contingency plans. The reuse of mitigation plans can make
it easier the conduction of this sub activity
- Analyze the cost-benefit relation of the mitigation actions
- It is important to realize that the mitigation actions bring extra cost
to the project. It is then necessary to evaluate if the benefits brought
by the risk mitigation steps are greater than the cost associated to their
implementation. The project manager must conduct a cost-benefit analysis
for every assumed risk. If the exposure to the risk is lower than the risk
mitigation cost, then it is better not to mitigate it but instead monitor
it throughout the project.
The product generated in this activity is the Project Risks Plan
that describes the identified risks, their priority, causes, consequences,
occurrence probability, impact, mitigation plan and contingency plan. The
next process activity is the integration of the risks plan into the project
plan. In this activity, the following sub activities are performed:
- Update the development process plan - In this sub activity,
the project manager must change the development process plan incorporating
the steps related to the risks mitigation plan.
- Update the project plan - In this sub activity, the project
manager changes the project plan, incorporating the costs associated to
the risks mitigation plans, the eventual resources added to the project
as well as all other changes that he/she considers to be caused by the
performed risks planning.
With the completion of this activity, the project plan is updated and
is completely integrated to the developed risks plan. The next process
activity is monitoring the project risks and it is divided as follows:
- Review the project risks plan -This review must be conducted
at the project established milestones, trying to observe if any risk has
become a problem, if it is about to become a problem, if the mitigation
plans are efficient, if any risk is no longer a problem or if new risks
came up. Based upon the new perception of each risk, some previous performed
activities can be reviewed. The following actions are related to monitoring
a risk: Mitigation strategy change, in case it becomes inefficient; definition
of a mitigation plan to any risk that becomes important; execution of a
pre-planned contingency plan; change of the risk status to concluded when
it no longer exists; inclusion of new risks in the project risks plan.
- Perform the necessary changes in the project risks plan - After
the review conducted at the project milestones, the risks plan must be
updated to reflect the changes performed in the continuously monitored
risks.
Risks monitoring make it possible to adequate the risks plan to the
new perception of the project risks. Next, we will discuss how the organizational
risk knowledge can support the execution of each one of the activities
and how it is captured throughout the process.
2.1 Reusing Organizational Risk Knowledge
The information related to the predicted or occurred risks in former
organization projects (such as their causes, consequences, their treatment
and success of the mitigation and contingency actions) may help the project
manager identify new project risks, estimate their probability and impact
and plan risk management. Besides, lessons learned regarding risk management
former projects might contribute to the enrichment of the project risk
planning.
The risks list that have occurred in former similar projects, i.e.,
risks that became problems, may help new project risks identification,
avoiding the situation in which potential problems could be forgotten or
not valued by the manager. Suppose, for instance, that a manager is identifying
risks in a project with certain characteristics and ignores the risks caused
by some conditions or restrictions. The verification of the risks that
occurred in similar projects may remind him of potential problems to be
faced in the project he/she is currently working on.
In the same way, risk data from similar projects may help project manager
during the estimates of risks occurrence likelihood and impact. Suppose,
for instance, that the manager is estimating the likelihood of occurrence,
causes and consequences and the impact associated to "high turnover"
risk. It is useful to analyze how this risk has behaved in similar organization
projects, verifying if it has become a problem, its consequences and impact
it has caused.
Knowing how many similar projects in which a risk was predicted and
how many projects in which a risk has occurred may also help the manager
in the estimating of risk likelihood occurrence. For instance, if risk
x occurred in 10 out of a total of 13 similar projects, the manager could
conclude that the risk has a high probability of occurrence in the project.
Inversely, if risk x occurred in zero out of a total of 13 similar projects,
the manager can conclude that the risk has a low probability of occurrence.
During the planning of mitigation and contingency actions, similar projects
risk data are also very useful. It is important to analyze the strategy
of risk treatment adopted in similar projects and verify the efficiency
of mitigation and contingency actions that were planned. This way, the
manager learns from the facts of former projects, avoiding the recurrence
of problems and reusing actions which were previously successful in the
risk mitigation or contingency. The lessons learned in former projects
concerning risk management also contribute a lot to the management of risks
in new projects. Throughout the process of risk management, it is recommended
to register the ideas and lessons learned by the project manager.
The risk data verification of similar projects requires the recovery
of similar projects to a specific project followed by the recovery of the
risks occurred in these projects. The approach of risk planning here described
uses a search for similar projects based on the direct participation of
the user.
After characterizing the software project, the project manager chooses
which criteria will be used in the search, according to its specific objective.
Examples of search objectives are to find similar projects aiming to identify
risks pertaining to the Personnel category; identify risks pertaining to
the Requirements category. Besides choosing the criteria to be used, the
manager also decides if the similar projects are recovered having as basis
all or at least one of the chosen criteria. Examples of criteria used in
project characterization are: Industry in which the software is inserted,
Type of software, Development paradigm, Nature of project, Experience level
of project managers, Experience level of development team, Experience level
of clients, Geographical distribution of team, Use of innovative technology
and Possible restrictions of the project (Schedule, Performance, Security
and Human Resources).
3 Experimental Study of the Relationships Between
Risk-Causing Facts and Risks
The first risk management activity accomplished in a project is the
identification of the project risks, where potential problems to be faced
by the development team and project management are identified. Failures
or items forgotten at this activity are propagated to the next risk management
process activities. Thus, it is essential to conduct a careful analysis
of all the facts that can potentially cause risks to the project.
Pfleeger et al. [Pfleeger et al., 2001]
points out the importance of analyzing the suppositions and decisions regarding
how a project will be carried out, who will take part on it and the resources
that will be needed to identify risks involved in each supposition and
decision taken by the project manager. Therefore, our risk planning approach
proposes the use of a checklist as a risk identification technique. This
checklist regards conditions and restrictions normally possible to be found
or predicted at the project planning phase with the associated risks caused
by them.
An experimental study was carried out to produce the checklist characterizing
the relationships between risk-causing facts and risks commonly found in
software projects. The process used for planning and executing the study
was based on the Wohlin et al. proposal [Wohlin et al,
2000] for experimentation processes. Study results were used to feed
checklist data making subjects' knowledge and experience regarding facts
and risks shareable by the use of such a technique for risks planning.
The following research goals were identified for our study. Using the
Goal-Question-Metric Paradigm [Basili et al., 1994],
these goals were refined in questions characterizing the main study aspects.
Metrics were also associated to the questions defined so that the data
could be collected to support answering the questions. To collect data
a questionnaire was prepared containing a set of 25 initial risk-causing
facts and a set of 15 initial risks, both of them based on risk management
technical literature. A characterization questionnaire was used to characterize
the subjects.
G1: Analyze the set of risk-causing facts for the purpose of
characterizing with respect to their use as risk factors
in project planning from the point of view of software project managers
in the context of software project risks planning.
G2: Analyze the set of risks for the purpose of characterizing
with respect to their use as risks in project planning from the
point of view of software project managers in the context of
software project risks planning.
G3: Analyze the set of risk-causing facts and the set of risks for
the purpose of characterizing with respect to the relationship
between risk-causing facts and risks from the point of view of software
project managers in the context of software project risks planning.
Subjects were chosen based on convenience. A total of 13 Brazilian software
project managers with relevant experience in risk management were selected.
Each subject was asked to exclude risk-causing facts and risks s/he considered
unnecessary, include risk-causing facts and risks s/he considered important
to be present at the sets and to explicitly mark down the relations between
software projects risk-causing facts and risks, based on their risk management
experience.
The characterization questionnaire information was used to group subjects
by experience and to define criteria to evaluate data. Doing so, it was
possible to collect project managers' opinions and experiences characterizing
a set of risk-causing facts that they believe normally occur in software
projects, a set of risks commonly found in software projects and the relations
that do exist between these risk-causing facts and risks. Table
1 presents the results obtained with the study.
4 The Riskplan Tool
Riskplan supports the identification, analysis, prioritization,
risk management planning and risk monitoring activities, defined in the
proposed risk management process. The tool guides the user during the execution
of the risk planning activities and it is integrated into an Enterprise-Oriented
Software Development Environment (i.e., a software development environment
that provides organizational knowledge required by software development
and maintenance processes and by their management [Villela
et al., 2001]).
Figure 2 shows the basic tool interface. On the
left side we can identify the risk management process and on the right
side the activity currently being performed by the user. The icons located
under the title bar allow the knowledge search and registration concerned
with process activities. The project manager can look for ideas and lessons
learned registered by previous projects managers and can also register
their own ideas and lessons. Throughout all risk management process, RiskPlan
also makes it available the explicit knowledge contained in the tool repository
concerning the activity that is being performed.

Figure 2: RiskPlan tool interface
The checklist (resulted from the experimental study) is available to
the project manager during the accomplishment of the activity "Identify
risks from project facts". As the manager selects the risks-causing
facts pertinent to the project, associated risks are displayed on the screen.
In case the manager believes a risk is not pertinent, s/he can uncheck
it and such risk will not be confirmed for the project risk list. Figure
2 illustrates the tool risk-causing fact checklist partially filled
in.
During the execution of the activity "Identify risks from similar
projects", the tool makes it available risk data that have been predicted
or have occurred in similar projects once the manager has characterized
the project. At this activity, RiskPlan presents to the manager the risks
occurred in previous similar projects and that were not yet identified
as pertinent to the current project, trying to prevent risk-causing facts
from being forgotten. Based on the list of risks presented, project manager
may use his/er personal experience to select among them those ones that
are applicable to the project. Besides, executing the activity "Identify
other risks" s/he can include new risks as that s/he judges necessary.
Once project risks have been identified, the manager queries the tool
risk knowledge repository to facilitate risks likelihood estimates and
impact and the definition of mitigation and contingency plans. Throughout
the whole risk management process data obtained from similar projects can
be consulted to support project manager analyzing risk behavior in the
various similar projects found. Once risks are analyzed, prioritized and
planned, the document Project Risks Plan may be generated and will serve
as basis for the Risk Management Process.
Table 1: Facts x Risks resulting from the experimental study
5 Final Considerations
Software project risk planning is carried out by project managers and
it requires an organization view, being strongly influenced by experiences
acquired in previous projects. The larger the experience of the project
manager the more s/he will be able to make risks identification, likelihood
and impact estimates and to define mitigation and contingency plans. This
paper has described an approach to support risk planning in software projects
offering project managers risk planning knowledge and experience acquired
throughout several organizational projects.
Among the main contributions of the approach here described, we point
out: (i) description of the risk management process based on the risk knowledge
management; (ii) definition of a risk identification strategy based on
the reuse of the organizational risk knowledge; (iii) definition of an
experimental study about the relations between software projects risk-causing
facts and risks, which can be used in future study replications; (iv) list
of the existent relationships between software project risk-causing facts
and risks, resulted from the study and (v) definition and implementation
of the RiskPlan tool, which supports the proposed approach.
Trying to improve and expand the risks planning approach that was proposed,
some future work perspectives are pointed out. First, an interesting work
would be repeat the experimental study carried out with project managers,
now with a new initial set of facts and risks and with more participants.
A new study would get the opinion and experience of others project managers
and would improve the checklist used as risks identification technique.
The risks planning approach that was proposed uses a search for similar
projects based on the direct participation of the user. After characterizing
the software project, the project manager chooses which criteria will be
used in the search, according to his specific objective. An interesting
future work would be the definition and implementation of an automated
search technique.
Acknowledgements
This study was partially supported by a grant from CAPES - Brazil that
the authors would like to thank. The authors also acknowledge the support
of CNPq -Brazilian Research Council to the Enterprise Oriented Software
Development Environment Project.
References
[Basili et al., 1994] Basili, V. R. , Caldiera,
G., Rombach, H. D. :"Goal Question Metric Paradigm". In John
J. Marciniak, editor, Encyclopedia of Software Engineering, volume 1, pages
528532. John Wiley & Sons (1994).
[Garvey et al., 1997] Garvey, P.R., Phair, D.J.,
Wilson, J.A.: "An Information Architecture for Risk Assessment and
Management", IEEE Software, 14, 3 (1997), 25-34.
[IEEE, 2001] IEEE Std 1540-2001: IEEE Standard
for Software Life Cycle Processes - Risk Management (2001).
[ISO, 1997] ISO 10006 : Quality Management - Guidelines
to Quality in Project Management (1997).
[ISO/IEC, 1999] ISO/IEC DTR 16326: "Software
Engineering - Guide for the application of ISO/IEC 12207 to project management"
(1999).
[Kontio and Basili, 1996] Kontio, J., Basili, V.R:
"Risk Knowledge Capture in the Riskit Method", Proceedings of
the 21st Software Engineering Workshop, NASA, Greenbelt, Maryland (1996).
[Markkula, 1999] Markkula, M.: "Knowledge
Management in Software Engineering Projects", Software Engineering
and Knowledge Engineering - SEKE 99; Kaiserlautern, Germany, June (1999).
[Pfleeger et al., 2001] Pfleeger, S. L., Haton,
L., Howell, C.C.: "Solid Software"; Prentice Hall (2001).
[Statz, 1999] Statz, J.: "Leverage your Lessons",
IEEE Software, 16, 2 (1999), 30-32
[Villela et al., 2001] Villela, K., Santos, G.,
Bonfim, C., et al.: "Knowledge Management in Software Development
Environments", 14th International Conference Software & Systems
Engineering and their Applications, Paris (2001).
[Wohlin et al., 2000] Wohlin, C., Runeson, P., Höst,
M., Ohlsson, M., Regnell, B., Wesslén, A: "Experimentation
in Software Engineering - An Introduction", Kluwer Academic Publishers
(2000).